Phase 7: Go Live

The go-live phase has tasks leading up to the go-live date, the day before, the day of, the day after, and the remainder of the week.

circle-check

Approach

The go-live approach will be documented in the go-live plan, which outlines:

  • Tasks required to transition the organization to the software

  • Support model during go-live

  • Dates and timelines

  • Required resources

  • Prerequisites and status for all activities

circle-info

These tasks will be developed and reviewed collaboratively with the project core team, RADPAIR, other vendors, and key stakeholders involved in the go-live process.

Go-Live Timeline

1

Pre Go-Live (1-2 Weeks Before)

  • Final system configuration verification

  • Integration testing sign-off

  • Training compliance verification

  • Go/no-go decision meeting

  • Communication to all stakeholders

2

Day Before Go-Live

  • Final system checks

  • Support team briefing

  • Command center setup

  • Communication reminders to users

  • Legacy system preparation

3

Go-Live Day

  • System activation

  • Command center operational

  • Real-time support and monitoring

  • Issue tracking and resolution

  • Status updates to leadership

4

Day After Go-Live

  • Morning status review

  • Issue prioritization and resolution

  • User feedback collection

  • Continued support coverage

  • Daily status report

5

Remainder of Week

  • Continued support with reduced intensity

  • Ongoing issue resolution

  • User adoption monitoring

  • Daily status updates

  • Transition planning to post go-live

Support

The go-live support structure will outline:

Element
Description

Resource Schedule

Coverage times for core team members, super users, radiologist super users, and project leadership

Command Center

Central hub for project team and help desk

Help Desk Process

Logging, tracking, and resolving issues

Communication Approach

Status updates and escalation procedures

Command Center

A dedicated command center will be established to serve as the central hub throughout the go-live period.

Command Center Components:

  • MS Teams call for virtual coordination

  • Physical command center (when appropriate)

  • Issue tracking system

  • Communication channels to all stakeholders

circle-exclamation

Support Team Coverage

Role
Go-Live Day
Day 2-3
Day 4-5

Project Leadership

Full coverage

Full coverage

As needed

Core Team Members

Full coverage

Full coverage

Reduced

Super Users

Full coverage

Full coverage

Reduced

Radiologist Super Users

Full coverage

Full coverage

On-call

RADPAIR Team

Full coverage

Full coverage

Reduced

Go-Live Plan Components

Your go-live plan should include:

Phase Deliverables

By the end of the Go-Live phase, you should have: